Projects North/West of St. Johns River
Contact: Madelene Skinner, HDR
626-9645 or e-mail
(jump to South/East projects)
|
Click on the project name to access scope and budget information *Note: Project construction schedules are currently being reassessed. |
| IN DESIGN |
|
CD |
PROJECT |
CONSTRUCTION START/FINISH |
| 10,12 |
Cahoon Road Phase 2 (Lenox to Beaver) |
TBD* |
| 14 |
Collins Road (Blanding to Pine Verde) |
TBD* |
| 11,14 |
Collins Road (Shindler to Old Middleburg) **Public Meeting Nov. 5** |
November 2009 Spring 2011 |
| 11,12,14 |
Collins Road (Shindler to Rampart) |
TBD* |
| 12 |
Crystal Springs Road Phase 2 (Hammond to Cahoon) |
TBD* |
| 11,12,14 |
Old Middleburg Road (103rd to Branan Field) |
TBD* |
| 10 |
Parramore Rd. Extension |
TBD* |
| 10,12 |
Ricker Road (Old Middleburg to Morse) |
TBD* |
| 11,12,14 |
Shindler Drive Phase 2 (Collins to 103rd) |
TBD* |
| UNDER CONSTRUCTION |
|
CD |
PROJECT |
ESTIMATED CONSTRUCTION FINISH |
| 8 |
Broward Road (I-95 to Lem Turner) |
Spring 2010 |
| 12,14 |
Collins Road Phase 2 (Rampart to Blanding) |
Spring 2010 |
| 12 |
Crystal Springs Road Phase 1 (Chaffee to Cahoon) |
Late 2010 |
| 7,8 |
Harts Road (Bertha to Dunn) |
Late 2009 |
| 9 |
McDuff & 5th Street Phase 2 (Beaver to Melson) |
Late 2010 |
| 9,10 |
New Kings Rd. Railroad Crossing |
Summer 2010 |
| 11 |
Starratt Road (New Berlin to Duval Station) |
Early 2010 |