Drainage Improvement Projects
The Jacksonville Stormwater Utility is responsible for overseeing the development and construction of large-scale drainage improvement projects in established neighborhoods. These projects are intended to both reduce flood conditions and provide treatment of pollutants of the stormwater. The stormwater fee funds these projects, which are generally approved annually in the city's Capital Improvement Plan (CIP).
For maintenance requests, such as ditch cleaning or drain line repair, please call 630-CITY (2489) or visit 630-CITY online. If you have questions about any of these projects, please e-mail stormwater@coj.net. Project dates listed below are current as of April 25, 2012. Date shifts may be attributed to unforeseen complications involving issues such as property acquisition or permitting.
Current Project Cost Estimates shown below may include, but may not be limited to, the cost for study, design, construction, and right of way acquisition, and may or may not be inclusive or representative of all funds available for the project.
CIP Estimates reflect the estimate listed for the project in the current year Capital Improvement Plan (CIP).
View projects in Phase 1 - Planning/Study, Phase 2 - Design, Phase 3 - Construction, or CIP Authorized
PROJECTS IN CONSTRUCTION (Phase 3)
| LINCOLN VILLA - PHASE 2 |
| Project Area |
Between Old Kings Rd. and Railroad Ave. (CD 8)
|
| Scope |
Continue neighborhood drainage improvements started in Phase 1.
|
| Budget |
$1.5 million |
| Start |
September 2010 |
| Finish |
Summer 2012 |
| Contact |
Thomas Waters, 255-8742 |
| PAUL AVENUE POND & OUTFALL |
| Project Area |
Area in the vicinity between Paul Avenue and Powers Avenue (CD 5)
|
| Scope |
Construct stormwater pond and perform outfall improvements to reduce local flooding.
|
| Budget |
$2.8 million |
| Start |
Pond - January 2012 (outfall still in design) |
| Finish |
Pond - Summer 2012 |
| Contact |
Paul Masters, 255-8717 |
Return to Top of Page
PROJECTS IN DESIGN (Phase 2)
-
Avenue B/Zinnia Ave Box Culvert
- Scope: Phase 1 is drainage improvements on Avenue B from Moncrief to approx. 600 feet south; Phase 2 is drainage improvements on Zinnia from the end of Phase 1 to Edgewood
- Location: Vicinity of Avenue B south of Moncrief Road (CD 10)
- Project Cost Estimate/Budget: $1.8 million
- Status: Bid and construction of Phase 1 are imminent; design of Phase 2 is underway.
-
Bunche Drive Pond
- Scope: Redesign existing treatment pond
- Location: Vicinity of Bunche Drive and Cleveland Road (CD 10)
- Current Project Cost Estimate/Budget: $1.5 million
- Schedule: Complete design early 2012, followed by bid and construction
-
Country Creek Area
- Scope: Construct improvements along Country Creek to alleviate flooding in the Hammond Forest and Country Creek neighborhoods.
- Location: Creek area between Hammond Blvd. and Fouraker Rd. (CD 12)
- Current Project Cost Estimate/Budget: $4.7 million
- Schedule: Complete design Spring 2013, followed by bid and construction
-
Hamilton/Jersey Drainage Improvements
- Scope: New outfall pipe Hamilton St. from Fremont to Ortega River; new pond at Fremont St. and Hamilton St.; neighborhood drainage improvements
- Location: Vicinity of Hamilton St. and Jersey St. (CD 9)
- Current Project Cost Estimate/Budget: $4 million
- Schedule: Complete design Summer 2012; followed by bid and construction.
-
Mandarin/Orange Picker Drainage Improvements
- Scope: Construct improvements to reduce flooding in the vicinity of the Worthington Glen, Gran Crique and Rivergate subdivisions.
- Location: Vicinity of Mandarin Road at Orange Picker Rd. (CD 6)
- Current Project Cost Estimate/Budget: $2.2 million
- Schedule: Complete design Spring 2012, followed by bid and construction.
-
McCoys Creek Pond "C"
- Scope: Construct stormwater pond to help relieve area flooding
- Location: Hollybrook Park, 319 Cherokee St. (CD 9)
- Current Project Cost Estimate/Budget: $2 million
- Schedule: Construction start early 2012
-
McCoys Creek Pond Retrofit (Air Liquide Site)
- Scope: Construct stormwater pond on the former Air Liquide site to help receive area flooding
- Location: Burke St. (CD 9)
- Current Project Cost Estimate/Budget: $1 million
- Schedule: Construction start early 2012
-
Miruelo Circle Drainage Improvements
- Scope: Improve drainage and runoff water quality and to create a more appealing and consistent look to the roadway throughout the project area
- Location: San Jose Estates subdivision off San Jose Blvd. (CD 5)
- Current Project Cost Estimate/Budget: $2.3 million
- Schedule: Design complete; bid and construction pending
Return to Top of Page
PROJECTS IN PLANNING/STUDY (Phase 1)
-
Crystal Springs Area Drainage
- Scope: TBD following engineering study
- Location: Vicinity of Crystal Springs Road and Blair Road (CD 12)
- CIP Estimate: $3.8 million
- Schedule: Design projected to be complete mid to late 2012.
-
Messer Area Drainage Improvements
- Scope: TBD following engineering study
- Location: Vicinity of Messer Rd. between Garden St. and Alligator's Rd.(CD 8)
- CIP Estimate: $4.75 million
- Schedule: Design projected to be complete late 2012.
-
Noroad/Lambing Drainage Improvements
- Scope: TBD following engineering study
- Location: Vicinity of Noroad and Lambing (CD 12)
- CIP Estimate: $1.4 million
- Schedule: Design projected to be complete mid to late 2012.
-
Old Plank Road Drainage Improvements
Return to Top of Page
ADDITIONAL PROJECTS AUTHORIZED IN CURRENT YEAR CIP
-
BAy Street Bridge at Hogan's Creek
- Scope: Continue bridge and outfall improvements started in 2008
- Location: East Bay Street at Hogan's Creek downtown (CD 7)
- CIP Estimate: $1 million
- Status: Re-start of construction pending
-
Lower Eastside pond Expansion
- Scope: Construct stormwater collection system to alleviate flooding
- Location: Area bound by 1st St to the south, Speaking St. to the west, 7th St. to the north and Harrison St. on the east (CD 7)
- CIP Estimate: $5.3 million
- Status: Start of design pending